‚Äč‚Äč‚Äč‚Äč‚Äč‚Äč‚Äč‚Äč‚Äč‚ÄčWestern School Division continues to see growth.  We will post updates on current capital projects on this page.‚Äč‚Äč

5 Year Capital Plan

The following is an update on key items listed in our 5 Year Capital Plan.

‚ÄčItem
‚ÄčDetails
Status‚Äč
‚ÄčNew School
‚ÄčK-8, on lot purchased by the division.  Daycare spaces to be included.  
Design phase to be completed by end of January 2022.
Potential construction start in the spring of 2022.
‚ÄčAdditional Future New School (On 5 Year Capital Plan)
‚ÄčConfiguration not yet determined.  Daycare consideration TBD.
‚ÄčRequest for approval for 2023-24
‚ÄčClassroom Addition to MCI
‚Äč‚Äč3 classroom addition to NW corner of MCI.  Will include a new science lab.

Design completed.
Construction phase fall of 2021

‚ÄčPiping Trades Addition (MCI)
‚ÄčRRTVA vocational programs (Welding+Piping) to be located together.  Division has purchased additional land beside the exisitng Welding Shop.
‚ÄčDesign completed.
Construction phase fall of 2021‚Äč

‚ÄčModular Classroom @ Minnewasta‚Äč
‚ÄčTo be moved from site of construction this fall.
‚ÄčCurrently being built and will be relocated and installed this fall.
‚ÄčModular Classrooms (2022-23)
‚Äč1 modular for each of Minnewasta, Maple Leaf and √Čcole Morden Middle Schools
‚ÄčFormal application will be in January of 2022
‚ÄčVarious School Roofing Projects
‚ÄčPreventative maitenance and repair.
In process
‚ÄčBoiler Replacement @ Maple Leaf School
‚ÄčReplacement of 2 legacy Boilers.
‚ÄčTender process to occur in late fall 2021.
‚ÄčPlayground Re-development
‚ÄčVarious projects at all schools.  Long-term replacement/upgrade of exisiting running track at MCI.
‚ÄčIn planning stages
‚Äč‚ÄčVarious other projects for the summer of 2021
‚ÄčCompletion of air-conditioning projects across the division.  Refurbishment of Science Labs at MCI.  LED lighting upgrades across schools.  New lift at √ČMMS.  Window replacement at some schools.  Yard refurbishment at √ČMMS.  Additional projects.
‚ÄčCompleted by September 1, 2021.
‚Äč‚Äč
‚Äč‚Äč



‚ÄčModular/Portable Classrooms

Portable.jpg

Western School Division currently has 18 modular classrooms with the 19th being added for September 2021.

‚ÄčSchool
‚ÄčModular Units
‚ÄčMinnewasta
‚Äč5 (+1 more for September 2021)
‚ÄčMaple Leaf
‚Äč8
‚Äč√Čcole Morden Middle School
5



Major Additions & Renovations

Western School Division has completed the intial design for the following projects for Morden Collegiate Institute.  These projects are both preparing to go to the tendering stage.  Construction is anticipated to begin in the early fall of 2021.
‚Äč

Morden Collegiate Institute


Classroom.jpg

A three classroom addition will be added to the north-west corner of MCI.  This will include basement, ground level and 2nd floor classrooms.  The 2nd floor classroom is designed as an additional science lab.‚Äč  This addition is approximately 3700 sq/ft.

InkedPiping Trades Addition_LI.jpg

A permanent home for the school's Piping Trades Program will be built on to the exisitng Welding Education Program.  ‚ÄčThis addition is approximately 5400 sq/ft.


New K-8 School

Site Map.jpg 

We are currently in the design phase for a new K-8 school at a site in the NW corner of Morden.  This school will built to house 600 students and will be able to support future additions to house a total of 800 students.  It will include approximately 75 childcare spaces.